Showing posts with label post and beam. Show all posts
Showing posts with label post and beam. Show all posts

Tuesday, September 18, 2012

retro posting: raising the first rib

     I have been asked countless times, " how id you get the big beams up." Here is is the how we did the first one. I climbed a tree, Hung a climbing harness in the tree, and ran a rope through a pulley on the harness. We took said rope and connected it to a truck a few hundred feet away via several redirecting pulleys. We connected the other end to the first timber rib.
     We lifted the rib to an angle so it would not just pull flat along the ground. Once we tipped the rib we placed blocks behind it so it would not slide.
All set. Rope attached to truck, Truck in gear, pulling forward. As we moved the truck forward the pine bent lower and lower. I thought the plan had failed. I parked the truck where it was and when I went to examine the situation I discovered that the rib now felt like a 2x4. It was essentially spring loaded by the bent tree. Allowing the spring of the tree to do the work we simply positioned the rib where we wanted it and lifted the holding blocks out of the way. We nailed some angled boards to the rib to keep it from tipping and the first rib was in place.
   The other ribs actually had to be lifted eight inches at a time due to the angle being incompatible with our new found spring loaded tree. This slow raising of the other ribs was definitely an exercise in trust and cooperation. Building this house has been one of the best forms of marriage counseling. It has taken communication to a whole new level.

Tuesday, September 11, 2012

second floor update

 The second floor is almost done. We have to a few windows to install and the stud work to support said windows. The roof is coming along nicely. We have all of the roof trusses up as of this past weekend. The pictures hearer show all but two trusses up. The photos also show the house before the North wall was built. More photos are to come. I often get distracted with building and forget to stop and take photos of the progress. We are using metal roofing and a radiant barrier on the roof. We nailed wide purlins in place to stabilize the trusses before placing the radiant barrier down. Once the radiant insulation was in place we nailed purlins on top of our wide purlins. These top purlins will allow us to screw the metal down while still maintaining an air space between the radiant insulation and the metal roof. This air gap is important in order for the radiant barrier to work properly, according to my reading.
The main floor is wrapped in tyvek. The windows are in and it is starting to feel like a real house. My next post will have the first photos of inside.

Monday, September 3, 2012

Second floor

       This past week has proved to be productive. Partly due to the threat of impending rain and partly because we made a conscious effort to build on multiple days. Unfortunately, I forgot to bring the camera for a daily snap shot. The photo to the left is our progress as of the end of the week.  The sub floor is done, save a small strip that will allow access to the crawl space. The second floor has half of the studs done. Yes, we are building the second floor with traditional framing as opposed to timber framing. Building the timber ribs was fun and interesting but there is no way we can safely raise ribs on a second floor. Not to mention we ran out of cured oak for the process. So, standard stud walls it is. We are using saw mill cut pine from the mill five miles away. 2x4x8s are 2.40 a board and that beats Lowes by a mile, not to mention it is locally sourced, cut and milled. Additionally, the wood from the mill is true cut as opposed to the "standard" lumber from the store that is labeled 2x4 but is really smaller.
      We were able to build a jig and finish half of our roof trusses this week. We lifted them into place with a reasonable amount of grunting and ladder climbing. The metal roofing and reflective bubble insulation was picked up this week and we will hopefully install it in the next couple days.
     Yesterday, amidst the rain, we burned four large piles of brush. Most of the brush was from clearing the site for the house. We also burned a large amount of brush from our recent clearing in the forest surrounding the house. The burning really helped to clean up the surrounding area and removing the downed brush from the forest will make room for our hazelnut planting this Fall.
    Below are several more pictures of the house in its current state, taken from different angles. The second to bottom photo is taken from the lower field and gives good perspective on how the house sits up on the hill.




Monday, August 27, 2012

Final rib


The final rib is upright and secured to the others with 4x4 beams. The 4x4 beams will serve as floor supports. They are lag screwed into the main 6x6 beams and extend out of the house. The extension of these beams will allow for connection the ceiling rafters to the front porch. The interconnection of all beams in the house help with stability and structure of the design. 

Stepping back to look at the structure. It is so rewarding to see the house with the actual end walls in place. It gives a real sense of the size and shape of the house. Standing up on the second floor joices gives an idea of the view and how the house is built into the edge of the forest. 


Sunday, August 26, 2012

Third Rib


The third rib is up, square and level. We have begun "mocking up" the future porch by laying a beam out to a pier. It is shaping up as planned and we will be ready for the second story soon. 

It is nice to see the lumber pile migrating into use as portions of the house. We are most of the way through the pile and will be in need of another run to the lumber mill soon. Considering the lumber mill is 4.8 miles away this should not be too much of a time suck. 

The sub floor is in in the bathroom as well as in part of the main house. We have left a access door into the crawl space so as to allow under house adventures and plumbing/ electric work as needed or when. It was nice to stand up on the future second floor and look down. It was also nice to catch a glimpse of what the view will be from the bedroom. 
The above photo shows our shameless use of lag bolts to hold the timber frame together. We did use angle bracing ( cherry in this case) to help keep the frame in square. While mortis and tenon would have been beautiful and is an honorable craft. It is not a craft I possess and so in the interest of stability the lag screws are countersunk into the frames, hidden but there.